Box Hill Building
Inspections
★★★★★ 4.8 on Google · 570+ reviews

Bored pier inspection in Box Hill

Depth, diameter and cage position, checked while the hole is still open.

  • After boring and cage placement, before any concrete
  • About 1 hour on site
  • Report within 24 hours
Price your Box Hill inspectionSend the address and the stage.

Fully licensed & accredited

Stage1 of 7
When to bookAfter boring and cage placement, before any concrete
Time on siteAbout 1 hour on site
Inspected againstAS 2870, AS 3600, the geotechnical report and the engineer's footing design

What is included in a Box Hill bored piers inspection

  • Pier positions and spacing against the footing plan
  • Pier diameter checked at the top of each hole
  • Depth against the engineer's design and the soil report
  • Founding material at the base where visible
  • Reinforcement cage size, laps and starter bars
  • Cover to the cage and centralisers
  • Hole cleanliness, spoil and loose material
  • Standing water or seepage before the pour
  • Steel projection into the slab or beam
  • Termite and service penetrations near piers
  • Set-out against the site plan and boundaries
  • Records and photographs for the engineer where required
Why it matters here

Bored piers inspections on Box Hill builds

Piers turn up on Box Hill lots where the engineering has to carry load through reactive Wianamatta clay to something firmer, and on the sloping ground toward the creek lines. Depth is the entire point of the exercise and it is the one thing nobody can verify afterwards, so the inspection has to sit between boring and concrete.

What we find at this stage in Box Hill

  • Pier depth short of the figure on the engineering
  • Cage off centre so cover is uneven around the pier
  • Loose spoil or standing water left in the base
  • Cage not seated at the bottom of the bore
  • Reinforcement inadequately supported before the pour
Steel element not installed as drawn, Box Hill
Steel element not installed as drawn
Sample findings

Sample defects found during our bored piers inspections in Box Hill

Annotated findings from Bored piers inspections on Box Hill builds. Client addresses withheld.

Beam detail, recorded during a frame inspection in Box Hill
Beam detail checked against the drawing
Weld or bolt at a steel beam, recorded during a frame inspection in Box Hill
Weld substituted where a bolt was detailed
Tension at a steel column, recorded during a frame inspection in Box Hill
Tension member at a steel column
Bolt at a steel column, recorded during a frame inspection in Box Hill
Bolt detail at a steel column

The other stages of a Box Hill build

  1. Slab pre-pour inspection in Box Hill2Slab pre-pourThe day before the pour, steel and formwork complete
  2. Frame inspection in Box Hill3FrameOnce frame and trusses are up and the roof is on, before lining
  3. Lock-up (pre-plaster) inspection in Box Hill4Lock-up (pre-plaster)After roof, cladding and external doors, before plaster
  4. Fixing inspection in Box Hill5FixingAfter mouldings, doors and joinery, before the painter
  5. Waterproofing inspection in Box Hill6WaterproofingAfter the membrane is applied and before any tile is laid
  6. Pre-handover (PCI) inspection in Box Hill7Pre-handover (PCI)Two to three weeks before your handover date

All construction stage inspections in Box Hill →

Guides

Construction stage guides for Box Hill

All guides →

Book a bored piers inspection in Box Hill

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Bored piers inspections in Box Hill: common questions

How long does a pier inspection take?

Under an hour on a standard residential lot, longer where the pier count is high or moving around the site is difficult.

What if a pier comes up short?

We put the depth we measured next to the depth that was required. Proposing a remedy belongs to the builder and their engineer; establishing the discrepancy while it is still visible is our part.

Are the footings certified by you?

No. Our observations are set against the engineering. Certifying a footing system is an engineer's function and the report says where one is needed.

Is water sitting in the bore a concern?

It can, because concrete placed into water does not reach its designed strength at the base. Recording it lets the bore be pumped out before the pour rather than argued about later.

How quickly can you attend?

Usually within a day. Piers are frequently bored and filled inside forty eight hours, so call when the date is set rather than when it is certain.

What should I supply?

Your lot's engineering drawing, showing pier depths, diameters and where each one sits. Lacking it, we can describe what is present but not confirm it against what was specified.

CallGet a Free Quote